  Partial Reference List - Condensate Polishing Plants (Under Execution)

Project Name Capacity & Configuration Scheduled Completion Period Project Owner

1 x 600MW Mettur Thermal Power Station

3 x 534 m3/hr

12 months

TNEB

2 x 600 MW Kalisindh Thermal Power Project.

6 x 537 m3/ hr

14 months

RRVUNL

2 x 500 MW Marwa Thermal Power Project Units 1 & 2

6 x 657 m3/hr

14 months

CSPGCL

2 x 500 MW Chandrapur
Thermal Power Project.

 6 x 710 m3/hr

14 months

MAHAGENCO

2 x 600 MW North Chennai Thermal Power Project
Unit- I &II

6 x 497  m3/ hr

12 months

BHEL

1 x 500 MW Ukai Thermal Power Station ,Unit-6

2 x 657 m3/ hr

12 months

BHEL

2 x 500 MW Tuticorin Thermal Power Plant

 4 x 661m3/ hr

12 months

NTPL

2 x 660 MW Tiroda Power Plant

6 x 822 m3/hr

12 months

Adani  Power

2 x 660 MW Kawai Power Plant

 6 x 822 m3/hr

12 months

Adani  Power

2 x 525 MW Monnet Power Project

4 x 683 m3/hr

15 months

BHEL

1 x 600 MW Avantha Power

2 x 800 m3/hr 15 months BHEL
 